Hanns-Martin-Schleyer Bridge culvert, full cut driving under compressed air, civil engineering and foundation construction (bored piles)
- Client
- EnBW Energie Baden-Württemberg AG
- Scope of services
- 49 pc. Drill-foundation piles each 20.00 m, Ø 0.90 to 1.20 m, rotary drilling rig BG 25 in use; 3,500 m³ earthmoving; partial filling of the excavation pits with liquid soil (approx. 609 m³); soil excavation with rotary drilling rig