Construction of a new pumping station
- Client
- SGD Süd Mainz Regionalstelle Wasser-Abfallwirtschaft (regional body for wastewater management)
- Scope of services
- Structure 36 x 8.50 x 12.61 m in-situ concrete construction (reinforced concrete) as a flood control pumping station subject to the requirements of the German Additional Technical Terms of Contract – Hydraulic Engineering (ZTV-W); 3,500 m² excavation, 1,840 m² (269 t) sheet piling, 163 t structural steel, demolition of old pumping station, 2,730 m³ terrain profiling, 1,768 m³ embankment filling